  Item #   5. B. 7.    
City Council
Meeting Date: 05/13/2019  
Submitted For: Steve Manek Submitted By: Rendi Wehr, Engineering

Information
Item
Approval of Change Order No. 1 to the Construction Contract with Haskell-Lemon Construction Co. for the FY17-18 Street Overlay Project; $162,116.17 Decrease.
Background
City Council approved Haskell-Lemon Construction Co.'s bid for the FY17-18 Street Overlay Project on August 28, 2017.  This change order is necessary to reconcile final quantities and fairly compensate the contractor.

The Base Bid was $904,387.60, plus Alternates 4, 5, 6, 8 and 12 for a total contract amount of $2,146,758.70.  This change order amends the total contract amount to $1,984,642.53.
Time Frame

Immediate upon approval.

Issue
Approval of this change order.
Recommendations
Staff recommends approval.
Action Needed
Motion to approve.
Public Notification
Posted City Council Agenda.

Fiscal Impact
Funding/Cost: $162.116.17 Decrease
Budgeted Item Y/N or N/A: Y
Account:
338007-8432 - 2000 CIP Sales Tax - Street Rehab Resurfacing & Reconstruction
Attachments
CO #1 FY17-18 Street Overlay Project