Item
Approval of Change Order No.2 to the Construction Contract with C4L LLC for the Monument Signs, Fence & Landscape Project; $5,653 increase.
Background
City Council awarded the original contract in the amount of $175,846.00 on June 25, 2018. This change order, in the amount not to exceed $5,653.00, in addition to one previously approved change order, amends the contract amount to $187,346.00. This change order is necessary to cover the cost of improving the lighting fixtures at the "Welcome" to Edmond sign and improving the readability of the Barnett Field sign. This work will fine tune the appearance of functionality of the signage.
Time Frame
Immediate upon approval.
Issue
Approval of this change order.
Recommendations
Approval.
Action Needed
Motion to approve.
Public Notification
Agenda posting.

Fiscal Impact
Funding/Cost: $5,653
Budgeted Item Y/N or N/A: Y
Account:
001163 - 8404 - Steetscape/Median Maintenance - Land Betterments; $1,152
116044- 8404 - Park Tax - Land Betterments; $4,501.00