  Item #   4. C. 8.    
City Council
Meeting Date: 03/11/2019  
Submitted For: Keith Stewart Submitted By: Keith Stewart

Information
Item
Approval of Change Order #2 to the construction contract with Globe Construction Company for the Historical Museum, Phase III; $8,123.
Background
There is one item included in change order number 2 to the construction contract with Globe Construction Company.  In an effort to improve the ceiling insulation R-Value at the museum, it was determined existing insulation above the acoustical ceiling in the collections area, corridors, offices, conference room, exhibit room and kids area needed to replaced.  This change order would fund the replacement of existing insulation with R19 insulation.  The total amount of this change order is $8,123, which is .95% of the total contract amount to date of $850,995.93.  This increases the total contract amount to $859,118.93.
Time Frame
Immediate upon approval.
Issue
Approval of change order number two, to replace ceiling insulation at the Historical Museum.
Recommendations
Staff recommends approval.
Action Needed
Motion to approve.
Public Notification
Posted Agenda

Fiscal Impact
Funding/Cost: $8,123
Budgeted Item Y/N or N/A: Y
Account:
338001-8405 Museum Restoration Project
Attachments
Historical Museum Phase III Change Order 2

AgendaQuick©2005 - 2020 Destiny Software Inc., All Rights Reserved