Approval of an Inter-Local Agreement between the City of Edmond and Board of County Commissioners of Oklahoma County for construction of an asphalt pavement surface on Danforth Road, between Douglas Boulevard and Post Road; $295,000.
Background
This mile of section line roadway continues to degrade and is insufficient to sustain current and anticipated daily traffic volumes.  This road was not constructed with a stabilized sub-base design, and is now experiencing significant degradation and failure.  Through a separate agreement, the sub-base of this mile of roadway is being reconstructed and stabilized, to include establishment/reestablishment of roadside drainage.  This agreement will include the construction of a five inch asphalt pavement surface and placing sod along the edge of the roadway.  The City of Edmond will reimburse Oklahoma County District #3 for the total cost to pave and sod this mile of roadway.
Time Frame
Immediate upon approval.
Issue
Approval of an inter-local agreement with the Board of County Commissioners, Oklahoma County to construct an asphalt pavement surface on this mile of roadway.
Recommendations
The Public Works Committee and staff recommends approval.
Action Needed
Motion to approve.
Public Notification
Posted Agenda

Fiscal Impact
Funding/Cost: $295,000
Budgeted Item Y/N or N/A: Y
Account:
001073-8432 Street and Alley
Attachments